| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Mar 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5653.07m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 04 Mar 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5636.57m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 02 Mar 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5576.07m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 01 Mar 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5552.07m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 29 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5521.87m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 28 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5509.67m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 27 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5498.87m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 26 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5483.97m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 24 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5475.35m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 23 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5464.35 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE |