NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works

Project NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Project Code PKDNABARD0117655
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Status Completed
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 250000000
AS Number G.O Rt (No.) 1070/2017/WRD dated 30/12/2017
TS Amount (Rs) 250000000
TS Number KWA/CE/NR/40/2017-18 dated 29/01/2018
Total Bill Submitted (Rs) 197796787
Total Bill Paid (Rs) 197796787
Population Benefitted 84813
Capacity in MLD 12.00
Actual Project Completion Date 30 Oct 2024
Coverage 3 Panchayaths- Agali,Sholayur& Pudur
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 NABARD-RIDF XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Oct 2024 ALL WORKS COMPLETED. Palakkad Proj AE 3
29 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. Palakkad Proj AE 3
28 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. Palakkad Proj AE 3
25 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB work is going on. Palakkad Proj AE 3
23 Oct 2024 Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. Palakkad Proj AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
06 Nov 2021 Contractor has been asked to supply pipes and pumps.The work should be commissioned by 28/2/2022 AEE,AE

Duration & Sanction dates

Date of start of Project 03/11/2018
Scheduled date of Completion of the Project 02 May 2020
Expected date of Completion 31/12/2024

Processing Dates

AS Date 30 Dec 2017
TS Date 29 Jan 2018

Other details