NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works

Project NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Project Code PKDNABARD0117655
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 250000000
AS Number G.O Rt (No.) 1070/2017/WRD dated 30/12/2017
TS Amount (Rs) 250000000
TS Number KWA/CE/NR/40/2017-18 dated 2/01/2018
Total Bill Submitted (Rs) 165600000
Total Bill Paid (Rs) 142874000
Population Benefitted 84813
Capacity in MLD 12.00
Actual Project Completion Date 30 Jun 2024
Coverage 3 Panchayaths- Agali,Sholayur& Pudur
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 NABARD-RIDF XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
15 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
14 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
13 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
10 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
06 Nov 2021 Contractor has been asked to supply pipes and pumps.The work should be commissioned by 28/2/2022 AEE,AE

Duration & Sanction dates

Date of start of Project 03/11/2018
Scheduled date of Completion of the Project 02 May 2020
Expected date of Completion 30/06/2023

Processing Dates

AS Date 30 Dec 2017
TS Date 29 Jan 2018