NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Project |
NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works |
Project Code |
PKDNABARD0117655 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
250000000
|
AS Number |
G.O Rt (No.) 1070/2017/WRD dated 30/12/2017 |
TS Amount (Rs) |
250000000 |
TS Number |
KWA/CE/NR/40/2017-18 dated 2/01/2018 |
Total Bill Submitted (Rs) |
165600000 |
Total Bill Paid (Rs) |
142874000 |
Population Benefitted |
84813 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
30 Jun 2024 |
Coverage |
3 Panchayaths- Agali,Sholayur& Pudur |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
NABARD-RIDF XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed |
Palakkad Proj AE 3 |
|
15 May 2024 |
Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed |
Palakkad Proj AE 3 |
|
14 May 2024 |
Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed |
Palakkad Proj AE 3 |
|
13 May 2024 |
Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed |
Palakkad Proj AE 3 |
|
10 May 2024 |
Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed |
Palakkad Proj AE 3 |
|
Review Date |
Review Message |
Review Attended By |
06 Nov 2021 |
Contractor has been asked to supply pipes and pumps.The work should be commissioned by 28/2/2022 |
AEE,AE |
Duration & Sanction dates
Date of start of Project |
03/11/2018 |
Scheduled date of Completion of the Project |
02 May 2020 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
30 Dec 2017 |
TS Date |
29 Jan 2018 |