NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works

Project NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
Project Code PKDNABARD0117655
Type Main project
Category NABARD
Description Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
District Palakkad
Execution Palakkad Project Dn
AS Amount (Rs) 250000000.00
Total Bill Submitted (Rs) 90247175.00
Total Bill Paid (Rs) 50086207.00
Coverage 3 Panchayaths- Agali,Sholayur& Pudur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Mar 2021 WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC concrete in progress. Filterhouse-Plastering in progress AE3 pkd
07 Mar 2021 WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC in progress. Filterhouse-Plastering in progress. AE3 pkd
01 Mar 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC completed. Filterhouse-Plastering in progress. AE3 pkd
25 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC in progress. Filterhouse-Plastering in progress. AE3 pkd
24 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-1st lift completed. Filterhouse-Plastering in progress. AE3 pkd

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Description Comments Issue Status
24 Mar 2020 25 Apr 2020 Pending Temporaray stoppage of ork due to migrant worker movement to native places Work resumed Solved
08 Aug 2019 07 Sep 2019 Pending Work stopped due to flood in Bhavani river Work resumed. contractor has severe damage due to the flood in the rive including loss of scaffoldings. Solved

Packages

No. Project Name Location View
1 NABARD-RIDF XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I Project Division Palakkad

Duration & Sanction dates

Date of Sanction 30/12/2017
Date of start 03/11/2018
Expected date of Completion 01/05/2021

Other details

Project Officers View
Funding Agency NABARD

Processing Dates

AS Date 30 Dec 2017
TS Date 29 Jan 2018