- Home
- NABARD-RIDF - XXIII- Comprehensive Water...
NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works
| Project |
NABARD-RIDF - XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works |
| Project Code |
PKDNABARD0117655 |
| Type |
Main project |
| Funding Agency |
NABARD |
| Category |
NABARD |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-98 (01) |
| Description |
Phase-I construction of RW Intake well cum pump house,12 MLD Water Treatement Plant,5LL Booster sump cum pump house, RW pumping main,CW gravity main, supply and erection of motor pump sets,transformers and allied works |
| Status |
Completed |
| District |
Palakkad |
| Executing Office |
Palakkad Project Dn |
| AS Amount (Rs) |
250000000
|
| AS Number |
G.O Rt (No.) 1070/2017/WRD dated 30/12/2017 |
| TS Amount (Rs) |
250000000 |
| TS Number |
KWA/CE/NR/40/2017-18 dated 29/01/2018 |
| Total Bill Submitted (Rs) |
197796787 |
| Total Bill Paid (Rs) |
197796787 |
| Population Benefitted |
84813 |
| Capacity in MLD |
12.00 |
| Actual Project Completion Date |
30 Oct 2024 |
| Coverage |
3 Panchayaths- Agali,Sholayur& Pudur |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
NABARD-RIDF XXIII- Comprehensive Water Supply Scheme to Agali and adjoining panchayaths in Mannarkkad Taluk in Palakkad district-Phase-I |
Project Division Palakkad |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 30 Oct 2024 |
ALL WORKS COMPLETED. |
Palakkad Proj AE 3 |
|
| 29 Oct 2024 |
WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited.
|
Palakkad Proj AE 3 |
|
| 28 Oct 2024 |
WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited.
|
Palakkad Proj AE 3 |
|
| 25 Oct 2024 |
WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB work is going on.
|
Palakkad Proj AE 3 |
|
| 23 Oct 2024 |
Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. |
Palakkad Proj AE 3 |
|
| Review Date |
Review Message |
Review Attended By |
| 06 Nov 2021 |
Contractor has been asked to supply pipes and pumps.The work should be commissioned by 28/2/2022 |
AEE,AE |
Duration & Sanction dates
| Date of start of Project |
03/11/2018 |
| Scheduled date of Completion of the Project |
02 May 2020 |
| Expected date of Completion |
31/12/2024 |
Processing Dates
| AS Date |
30 Dec 2017 |
| TS Date |
29 Jan 2018 |