| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Jan 2021 | WTP Filterhouse roofslab RCC completed. WW Tank roof slab completed.Chemical house roof slab completed. CW Sump Haunch2nd lift sidewall completed.earth work for clarifier-2 in progress | Palakkad Proj AE 3 | |
| 25 Jan 2021 | WTP Filterhouse roofslab RCC completed. WW Tank roof slab completed.Chemical house roof slab completed. CW Sump Haunch2nd lift sidewall completed. | Palakkad Proj AE 3 | |
| 18 Dec 2020 | WTP Filterhouse roofslab RCC completed. WW Tank sidewall RCC in progres. CW Sump Haunch completed. | Palakkad Proj AE 3 | |
| 23 Nov 2020 | 12.00mld WTP- Clarifier-1- Structural works completed. Filterhouse- Structural works of roof slab ongoing. Sump cum pumphouse- Earthwork completed. | Palakkad Proj AE 3 | |
| 17 Nov 2020 | 9.00m Dia Wellcumpumphouse-Completed-90%,5.00LL sump cum booster-completed-90%, 12.00MLD WTP- completed-40%, RWPM&CWPM-not started | Palakkad Proj AE 3 |