Status Date Overall Project Status Project Officer Contact
07 Nov 2021 WTP structural work completed,Pipes and pumpsets to be supplied Palakkad Project Dn EE
13 Jun 2021 WTP approach road work in progress. Structural works of clear water of FH channel in progress. Palakkad Proj AE 3
02 Jun 2021 WTP approach road work in progress. Structural works of clarifier-1&2, Filterhouse, CW sump PH completed. Finishing works in progress. Palakkad Proj AE 3
09 Mar 2021 WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC concrete in progress. Filterhouse-Plastering in progress Palakkad Proj AE 3
07 Mar 2021 WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC in progress. Filterhouse-Plastering in progress. Palakkad Proj AE 3
01 Mar 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC completed. Filterhouse-Plastering in progress. Palakkad Proj AE 3
25 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC in progress. Filterhouse-Plastering in progress. Palakkad Proj AE 3
24 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-1st lift completed. Filterhouse-Plastering in progress. Palakkad Proj AE 3
20 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-Baseslab& haunch RCC competed. Filterhouse-Plastering in progress. Palakkad Proj AE 3
18 Feb 2021 WTP- CW Sump Coverslab RCC in progress.clarifier-2-Baseslab& haunch RCC competed. Filterhouse-Plastering in progress. Palakkad Proj AE 3