| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Nov 2021 | WTP structural work completed,Pipes and pumpsets to be supplied | Palakkad Project Dn EE | |
| 13 Jun 2021 | WTP approach road work in progress. Structural works of clear water of FH channel in progress. | Palakkad Proj AE 3 | |
| 02 Jun 2021 | WTP approach road work in progress. Structural works of clarifier-1&2, Filterhouse, CW sump PH completed. Finishing works in progress. | Palakkad Proj AE 3 | |
| 09 Mar 2021 | WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC concrete in progress. Filterhouse-Plastering in progress | Palakkad Proj AE 3 | |
| 07 Mar 2021 | WTP- CW Sump Coverslab RCC completed.clarifier-2-3rd lift RCC in progress. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 | |
| 01 Mar 2021 | WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC completed. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 | |
| 25 Feb 2021 | WTP- CW Sump Coverslab RCC in progress.clarifier-2-2nd lift RCC in progress. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 | |
| 24 Feb 2021 | WTP- CW Sump Coverslab RCC in progress.clarifier-2-1st lift completed. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 | |
| 20 Feb 2021 | WTP- CW Sump Coverslab RCC in progress.clarifier-2-Baseslab& haunch RCC competed. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 | |
| 18 Feb 2021 | WTP- CW Sump Coverslab RCC in progress.clarifier-2-Baseslab& haunch RCC competed. Filterhouse-Plastering in progress. | Palakkad Proj AE 3 |