| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. | Palakkad Proj AE 3 | |
| 15 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. | Palakkad Proj AE 3 | |
| 14 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing.73% completed | Palakkad Proj AE 3 | |
| 13 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing.73% completed | Palakkad Proj AE 3 | |
| 12 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing.73% completed | Palakkad Proj AE 3 | |
| 11 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing.73% completed | Palakkad Proj AE 3 | |
| 10 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL. Pumpsets & Transformer to supplied at site. Boundary wall work in progress,All plastering work in finishing stage,Well pitching work in progress Access road work in progress .Filter house hand rail work in progress 73% completed | Palakkad Proj AE 3 | |
| 09 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL. Pumpsets & Transformer to supplied at site. Boundary wall work in progress,All plastering work in finishing stage,Well pitching work in progress Access road work in progress .Filter house hand rail work in progress 73% completed | Palakkad Proj AE 3 | |
| 08 Feb 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL. Pumpsets & Transformer to supplied at site. Boundary wall work in progress,All plastering work in finishing stage,Well pitching work in progress Access road work in progress .Filter house hand rail work in progress | Palakkad Proj AE 3 | |
| 07 Feb 2022 | PUMP AND PIPES to be supplied,Boundary wall work in progress,All plastering work in finishing stage,Well pitching work in progress Access road work in progress .Filter house hand rail work in progress | Palakkad Proj AE 3 |