Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Feb 2021 WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress Palakkad Proj AE 3
11 Feb 2021 WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress Palakkad Proj AE 3
10 Feb 2021 WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress Palakkad Proj AE 3
08 Feb 2021 WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed Palakkad Proj AE 3
07 Feb 2021 WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed Palakkad Proj AE 3
06 Feb 2021 WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed Palakkad Proj AE 3
05 Feb 2021 WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 earthwork completed Palakkad Proj AE 3
04 Feb 2021 WTP- CW Sump 4th lift reinforcement in progress. Palakkad Proj AE 3
03 Feb 2021 WTP- CW Sump 3rd lift sidewall completed. clarifier-2 inlet&scour pipe laid. Palakkad Proj AE 3
02 Feb 2021 WTP- CW Sump 3rd lift sidewall completed. earth work for clarifier-2 in progress Palakkad Proj AE 3