| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Feb 2021 | WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress | Palakkad Proj AE 3 | |
| 11 Feb 2021 | WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress | Palakkad Proj AE 3 | |
| 10 Feb 2021 | WTP- CW Sump 4th lift RCC competed.clarifier-2-Baseslab RCC in progress | Palakkad Proj AE 3 | |
| 08 Feb 2021 | WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed | Palakkad Proj AE 3 | |
| 07 Feb 2021 | WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed | Palakkad Proj AE 3 | |
| 06 Feb 2021 | WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 PCC completed | Palakkad Proj AE 3 | |
| 05 Feb 2021 | WTP- CW Sump 4th lift reinforcement in progress.clarifier-2 earthwork completed | Palakkad Proj AE 3 | |
| 04 Feb 2021 | WTP- CW Sump 4th lift reinforcement in progress. | Palakkad Proj AE 3 | |
| 03 Feb 2021 | WTP- CW Sump 3rd lift sidewall completed. clarifier-2 inlet&scour pipe laid. | Palakkad Proj AE 3 | |
| 02 Feb 2021 | WTP- CW Sump 3rd lift sidewall completed. earth work for clarifier-2 in progress | Palakkad Proj AE 3 |