| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 10 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 09 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 08 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. | Palakkad Proj AE 3 | |
| 08 Mar 2022 | RWPM 400 mm DI pipes Laying started . Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. | Palakkad Proj AE 3 | |
| 07 Mar 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. over all 73%completed | Palakkad Proj AE 3 | |
| 05 Mar 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. over all 73%completed | Palakkad Proj AE 3 | |
| 04 Mar 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. over all 73%completed | Palakkad Proj AE 3 | |
| 02 Mar 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. over all 73%completed | Palakkad Proj AE 3 | |
| 01 Mar 2022 | Supply order for 400 mm DI pipes for a length of 3240m(50%) has been placed to m/s ESL on 27/01/22. Pumpsets & Transformer to be supplied at site. Finishing of WTP, Intake well& Booster are in progress. Compound wall, approach road, primary coat painting are ongoing. over all 73%completed | Palakkad Proj AE 3 |