| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Apr 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.Over all 80% completed | Palakkad Proj AE 3 | |
| 03 Apr 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 80% completed | Palakkad Proj AE 3 | |
| 02 Apr 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 80% completed | Palakkad Proj AE 3 | |
| 01 Apr 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 31 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 30 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 26 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 25 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 24 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 | |
| 23 Mar 2022 | 1485m (out of 6635m)of 400mm DI K9 pipe recieved at site. Bhavani River crossing through the riverbed location identified &trial pit taken at the location. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. VT& CF pumpsets & transformer to be supplied by the contractor. over all 75% completed | Palakkad Proj AE 3 |