| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 19 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 18 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 13 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 11 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 09 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 07 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 04 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 02 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 31 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 |