Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Nov 2021 |
Work in progress | 30% Completed | 07/11/2021
Total 130.0016 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 45293.8 laid 2).90mm pvc 6kg- 35.600km supplied and 43364.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2136.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 5855.20 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--259.00m laid 15) 300mm DI –PIPE-1311.00m laid Meenakshipuram tank-plastering work started. Total connection -2333.00Nos connection provided Total Nallepilly-107No, Perumatty No.-918, Pattenchery-112 Nos total 1137.00 nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos) |
Chittur Project Dn - AE 1 |
|
06 Nov 2021 |
Work in progress | 30% Completed | 06/11/2021
Total 130.0016 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 45293.8 laid 2).90mm pvc 6kg- 35.600km supplied and 43364.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2136.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 5855.20 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--259.00m laid 15) 300mm DI –PIPE-1311.00m laid Meenakshipuram tank-plastering work started. Total connection -2333.00Nos connection provided Total Nallepilly-107No, Perumatty No.-918, Pattenchery-112 Nos total 1137.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) |
Chittur Project Dn - AE 1 |
|
01 Nov 2021 |
379 No- cc first bill
1421.00-cc second bill
total-1800 Nos FHTC billed |
Chittur Project Dn - AE 1 |
|
31 Oct 2021 |
Work in progress | 30% Completed | 31/10/2021
Total 123.613 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 43241.8 laid 2).90mm pvc 6kg- 35.600km supplied and 41631.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2046.60m laid 6).350mm DI- 1562 m supplied and 1739.500 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4998.60 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Meenakshipuram tank-cover slab concrete work completed. Total connection -2063 Nos connection provided Total Nallepilly-91No, Perumatty No.-834, Pattenchery-107 Nos total 1032.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) |
Chittur Project Dn - AE 1 |
|
28 Oct 2021 |
Total 122.613 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 43241.8 laid 2).90mm pvc 6kg- 35.600km supplied and 41631.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2046.60m laid 6).350mm DI- 1562 m supplied and 1739.500 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4998.60 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Meenakshipuram tank-cover slab concrete work completed. Total connection -2063 Nos connection provided Total Nallepilly-91No, Perumatty No.-834, Pattenchery-107 Nos total 1032.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) |
Chittur Project Dn - AE 1 |
|
24 Oct 2021 |
Work in progress | 29% Completed | 24/10/2021
Total 121.120 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 43241.8 laid 2).90mm pvc 6kg- 35.600km supplied and 40887.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1735.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4470.60m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Meenakshipuram tank-cover slab concrete work completed. Total connection -2063 Nos connection provided Total Nallepilly-91No, Perumatty No.-834, Pattenchery-107 Nos total 1032.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) |
Chittur Project Dn - AE 1 |
|
20 Oct 2021 |
Work in progress | 28% Completed | 20/10/2021
Total 120.120 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 43241.8 laid 2).90mm pvc 6kg- 35.600km supplied and 40887.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1735.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4470.60m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Meenakshipuram tank-cover slab concrete work completed. Total connection -2063 Nos connection provided Total Nallepilly-91No, Perumatty No.-834, Pattenchery-107 Nos total 1032.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) |
Chittur Project Dn - AE 1 |
|
17 Oct 2021 |
Work in progress | 28% Completed | 17/10/2021
Total distribution length laid - 105.79 Km Nallepilly panchayth - 14.676 km Perumatty panchayath - 67.025km Pattencherry panchayath - 24.090 km Total pumping main to Meenakshipuram OHSR - 5.000km laid Meenakshipuram OHSR - cover slab concrete arranged tomorrow |
Chittur Project Dn - AE 1 |
|
10 Oct 2021 |
Work in progress | 28% Completed | 10/10/2021
Total 118.564 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 42107.80m laid 2).90mm pvc 6kg- 35.600km supplied and 40269m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1735.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4264.10m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Total connection -1698.00 Nos FHTC provided Total Nallepilly-91No, Perumatty No.-832 ,Pattenchery-107 Nos total 1032.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram 6 LL tank- side wall third lift concrete work comple |
Chittur Project Dn - AE 1 |
|
04 Oct 2021 |
Work in progress | 27% Completed | 04/10/2021
Total 117.784 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 41999.80 m laid 2).90mm pvc 6kg- 35.600km supplied and 39753.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1735.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4264.10m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Total connection -1698.00 Nos FHTC provided Total Nallepilly-47 No, Perumatty No.-832 ,Pattenchery-107 Nos total 986.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- side wall second lift concrete work completed.) |
Chittur Project Dn - AE 1 |
|