Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Jul 2021 Work in progress | 15% Completed | 09/07/2021 Total 61.0068 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3618m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) Chittur Project Dn - AE 1
03 Jul 2021 Work in progress | 13% Completed | 03/07/2021 Total 59.604km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 22394.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1284.00 m laid 160mm pvc 6 kg-3000m supplied and 3998 m laid 140mm pvc-6 kg-3000m supplied-840m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-463,Pattenchery-58 Nos total 522.00 nos of FHTC provided, meenakshipuram 6LL OHSR- Plinth beam shuttering and reinforcement work in progress Chittur Project Dn - AE 1
29 Jun 2021 Work in progress | 13% Completed | 29/06/2021 Total 58.572 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 22394.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided Chittur Project Dn - AE 1
28 Jun 2021 Work in progress | 13% Completed | 28/06/2021 Total 58.572 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 22394.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided 6LL OHSR-Column footing work started Chittur Project Dn - AE 1
25 Jun 2021 Meenakhipuram 6 LL OHSR pcc work started Chittur Project Dn - AE 1
25 Jun 2021 Work in progress | 13% Completed | 25/06/2021 Total 58.472 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 22294.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided Chittur Project Dn - AE 1
20 Jun 2021 Work in progress | 12% Completed | 20/06/2021 12% of work complete Total 55.39700 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22342.80m laid 90mm pvc 6kg- 30km supplied and 19381.40 m laid 90mm pvc 10 kg-3444.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided Chittur Project Dn - AE 1
14 Jun 2021 12% of work complete Total 54.39700 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 21342.80m laid 90mm pvc 6kg- 30km supplied and 19381.40 m laid 90mm pvc 10 kg-3444.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided Chittur Project Dn - AE 1
08 Jun 2021 Work in progress | 12% Completed | 08/06/2021 12% of work complete Total 53.39700 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 20342.80m laid 90mm pvc 6kg- 30km supplied and 19381.40 m laid 90mm pvc 10 kg-3444.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1182.00 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-422,Pattenchery-58 Nos total 481.00 nos of FHTC provided Chittur Project Dn - AE 1
01 Jun 2021 Work in progress | 10% Completed | 27/05/2021 9% of work complete Total 42.860 km pipe laid 90mm pvc pipe -8kg-12498 m supplied and 12895.00m laid 90mm pvc 6kg- 15898 m supplied and 18433.40 m laid 90mm pvc 10 kg-2751.00m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1761.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-322,Pattenchery-58 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1