Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Oct 2021 |
Work in progress | 27% Completed | 02/10/2021
Total 116.975 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 41459.80 m laid 2).90mm pvc 6kg- 35.600km supplied and 38799.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1735.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 4205.00m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 6162.50m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid , 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--247.00m laid Total connection -1698.00 Nos FHTC provided Total Nallepilly-47 No, Perumatty No.-832 ,Pattenchery-107 Nos total 986.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- side wall second lift concrete work completed.) |
Chittur Project Dn - AE 1 |
|
27 Sep 2021 |
Work in progress | 27% Completed | 27/09/2021
Total 107.7604 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 41459.80 m laid 2).90mm pvc 6kg- 35.600km supplied and 36598.00 m laid 3).90mm pvc 10 kg-7646.00m laid and 5000 m supplied 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1622.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 2620.50m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied - 2698.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 6155.00 m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid , 13).160mm pvc -10kg-833.50m laid 14).80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-47 No, Perumatty No.-779 ,Pattenchery-107 Nos total 933.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- HAUNCH first lift concrete work completed.) |
Chittur Project Dn - AE 1 |
|
24 Sep 2021 |
Work in progress | 27% Completed | 24/09/2021
Total 105.5604 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 41459.80 m laid 2).90mm pvc 6kg- 33.600km supplied and 36598.00 m laid 3).90mm pvc 10 kg-7646.00m laid and 5000 m supplied 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1622.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 2420.50m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied - 2698.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 6155.00 m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid , 13).160mm pvc -10kg-833.50m laid 14).80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-47 No, Perumatty No.-779 ,Pattenchery-107 Nos total 933.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- HAUNCH first lift concrete work completed.) |
Chittur Project Dn - AE 1 |
|
20 Sep 2021 |
Work in progress | 27% Completed | 20/09/2021
Total 104.5604 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 40459.80 m laid 2).90mm pvc 6kg- 33.600km supplied and 36598.00 m laid 3).90mm pvc 10 kg-7646.00m laid and 5000 m supplied 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 1870.60m laid 6).350mm DI- 1562 m supplied and 1622.00 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 2420.50m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied - 2698.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 6155.00 m laid 12).140mm pvc-6 kg-3000m supplied-3798m laid , 13).160mm pvc -10kg-833.50m laid 14).80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-42 No, Perumatty No.-739 ,Pattenchery-95 Nos total 876.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- HAUNCH first lift concrete work completed.) |
Chittur Project Dn - AE 1 |
|
14 Sep 2021 |
Work in progress | 27% Completed | 14/09/2021
Total 94.9805 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 40459.80 m laid 90mm pvc 6kg- 33.600km supplied and 36598.00 m laid 90mm pvc 10 kg-7646.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 1622.00 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 740.50m laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2698.00 m laid 160mm pvc 6 kg-4352.00m supplied and 5481.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid 80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-42 No, Perumatty No.-739 ,Pattenchery-95 Nos total 876.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- HAUNCH first lift concrete work completed. |
Chittur Project Dn - AE 1 |
|
09 Sep 2021 |
Work in progress | 27% Completed
Total 93.9805 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 39459.80 m laid 90mm pvc 6kg- 33.600km supplied and 36598.00 m laid 90mm pvc 10 kg-7646.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 1622.00 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 740.50m laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2698.00 m laid 160mm pvc 6 kg-4352.00m supplied and 5481.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid 80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-42 No, Perumatty No.-739 ,Pattenchery-95 Nos total 876.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- HAUNCH first lift concrete work completed.
|
Chittur Project Dn - AE 1 |
|
04 Sep 2021 |
Work in progress | 27% Completed | 04/09/2021
Total 85.9315 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 33894.80 m laid 90mm pvc 6kg- 33.600km supplied and 29546.00 m laid 90mm pvc 10 kg-7406.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 740.50m laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2262.00 m laid 160mm pvc 6 kg-4352.00m supplied and 4551.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid 80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-668 ,Pattenchery-88 Nos total 757.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank- floor slan concrete work completed. |
Chittur Project Dn - AE 1 |
|
29 Aug 2021 |
Work in progress | 24% Completed | 29/08/2021
Total 82.9315 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 30894.80 m laid 90mm pvc 6kg- 33.600km supplied and 29546.00 m laid 90mm pvc 10 kg-7406.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 740.50m laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2262.00 m laid 160mm pvc 6 kg-4352.00m supplied and 4551.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid 80mm GI pipe--247.00m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-668 ,Pattenchery-88 Nos total 757.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank-6LL -FLOOR SLAB shuttering work in progress
|
Chittur Project Dn - AE 1 |
|
16 Aug 2021 |
Work in progress | 22% Completed | 16/08/2021
Total 78.4875 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 30492.80 m laid 90mm pvc 6kg- 33.600km supplied and 27113.00 m laid 90mm pvc 10 kg-7046.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 291.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2154.00 m laid 160mm pvc 6 kg-4352.00m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-668 ,Pattenchery-88 Nos total 757.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram tank-Above IInd brace beam column Ist lift and IInd lift concrete progressing at Meenakshipuram 6LL OHSR and 7th flight stair concrete progressing at Meenakshipuram 6LL OHSR |
Chittur Project Dn - AE 1 |
|
12 Aug 2021 |
Work in progress | 21% Completed | 12/08/2021
Total 77.4875 km pipe laid 90mm pvc pipe -8kg- 37.098 k m supplied and 29492.80 m laid 90mm pvc 6kg- 33.600km supplied and 27113.00 m laid 90mm pvc 10 kg-7046.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI- Supplied and 27.50M laid 200mm DI- 1749m Supplied and 291.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 2154.00 m laid 160mm pvc 6 kg-4352.00m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-668 ,Pattenchery-88 Nos total 757.00 nos of FHTC provided ( cc first and part bill-379 Nos FHTCs billed) Meenakshipuram 6 LL Tank- COLUMN CONCRETE above second brace work in progress |
Chittur Project Dn - AE 1 |
|