Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Aug 2021 |
Work in progress | 20% Completed | 09/08/2021
Total 72.188 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 29492.80 m laid 90mm pvc 6kg- 30km supplied and 23222.00 m laid 90mm pvc 10 kg-6444.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-652 ,Pattenchery-62 Nos total 715.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) first brace concrete work complete and reinforcement work for column work started at Meenakshipuram 6LL OHSR.Column second lift (Above Ist brace ) concrete progressing at Meenakshipuram 6LL OHSR. Pwd restoration work started at Vilayodi Vembra road 90mm pvc pipe 10 kg laying in Cheriya Mullanthode Kizhkkekalam in Perumatty panchayath Linking work in progress at Chembattpalam (KIIFB work) Pattanchery panchayath GSB laying work progressing at Vilayodi Vembra road near Karuna hospital
6LL meenakshipuram tank- second brace beam concrete work in progress |
Chittur Project Dn - AE 1 |
|
01 Aug 2021 |
Work in progress | 17% Completed | 01/08/2021
Total 68.026 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 28348.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-652 ,Pattenchery-62 Nos total 715.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) first brace concrete work complete and reinforcement work for column work started at Meenakshipuram 6LL OHSR.Column second lift (Above Ist brace ) concrete progressing at Meenakshipuram 6LL OHSR. Pwd restoration work started at Vilayodi Vembra road 90mm pvc pipe 10 kg laying in Cheriya Mullanthode Kizhkkekalam in Perumatty panchayath Linking work in progress at Chembattpalam (KIIFB work) Pattanchery panchayath GSB laying work progressing at Vilayodi Vembra road near Karuna hospital |
Chittur Project Dn - AE 1 |
|
27 Jul 2021 |
Work in progress | 17% Completed | 27/07/2021
Total 67.026 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 27348.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-652 ,Pattenchery-62 Nos total 715.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) first brace concrete work complete and reinforcement work for column work started at Meenakshipuram 6LL OHSR. |
Chittur Project Dn - AE 1 |
|
24 Jul 2021 |
Work in progress | 17% Completed | 24/07/2021 Total 65.75 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 26904.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) first brace concrete work progress at Meenakshipuram 6LL OHSR. |
Chittur Project Dn - AE 1 |
|
24 Jul 2021 |
Work in progress | 17% Completed | 24/07/2021 Total 65.75 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 26904.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) Shuttering work and Basement earth filling progressing at Meenakshipuram 6LL OHSR. |
Chittur Project Dn - AE 1 |
|
24 Jul 2021 |
Work in progress | 16% Completed | 19/07/2021 Total 64.75 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 25904.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) First brace concrete work in progress at Meenakshipuram 6LL OHSR. |
Chittur Project Dn - AE 1 |
|
24 Jul 2021 |
Work in progress | 17% Completed | 24/07/2021 Total 64.75 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 25904.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3798m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) Shuttering work and Basement earth filling progressing at Meenakshipuram 6LL OHSR. |
Chittur Project Dn - AE 1 |
|
20 Jul 2021 |
Work in progress | 16% Completed | 19/07/2021
Total 64.75 km pipe laid
90mm pvc pipe -8kg-35.988k m supplied and 25904.80m laid
90mm pvc 6kg- 30km supplied and 23042.40 m laid
90mm pvc 10 kg-3606.00m laid and 5000 m supplied
500mm DI-K9 pipe-250m supplied and 184.50 m laid
450mm DI - 1650 m supplied and 1870.60m laid
350mm DI- 1562 m supplied and 811 m laid
250mm DI-27.50M laid
20 mm pvc 12.50 kg 1998 m supplied
110mm pvc 6 kg-3000m supplied - 1398.00 m laid
160mm pvc 6 kg-3000m supplied and 4106.00 m laid
140mm pvc-6 kg-3000m supplied-3798m laid ,
160mm pvc -10kg-833.50m laid
FHTC provided Total
Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed) Shuttering work and Basement earth filling progressing at Meenakshipuram 6LL OHSR.
|
Chittur Project Dn - AE 1 |
|
19 Jul 2021 |
Work in progress | 16% Completed | 19/07/2021
Total 61.664 km pipe laid 90mm pvc pipe -8kg-35.988k m supplied and 23000.00m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid and 5000 m supplied 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3618m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed)
Shuttering work and Basement earth filling progressing at Meenakshipuram 6LL OHSR.
|
Chittur Project Dn - AE 1 |
|
11 Jul 2021 |
Work in progress | 15% Completed | 11/07/2021
Total 61.1068 km pipe laid 90mm pvc pipe -8kg-30.990k m supplied and 22442.80m laid 90mm pvc 6kg- 30km supplied and 23042.40 m laid 90mm pvc 10 kg-3606.00m laid 500mm DI-K9 pipe-250m supplied and 184.50 m laid 450mm DI - 1650 m supplied and 1870.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1398.00 m laid 160mm pvc 6 kg-3000m supplied and 4106.00 m laid 140mm pvc-6 kg-3000m supplied-3618m laid , 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-601,Pattenchery-58 Nos total 660.00 nos of FHTC provided( cc first and part bill-379 Nos FHTCs billed)
|
Chittur Project Dn - AE 1 |
|