Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jul 2024 | 44.642km laying ,1382nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
22 Jul 2024 | 44.642km laying ,1293nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
12 Jul 2024 | 44.642km laying ,1228nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
03 Jul 2024 | 44.642km laying ,1057nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
25 Jun 2024 | 44.642km laying ,958nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
20 Jun 2024 | 44.642km laying ,888nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
10 Jun 2024 | 44.642km laying ,674nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
01 Jun 2024 | 44.642km laying ,424nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
22 May 2024 | 44.642km laying ,424nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
17 May 2024 | 44.5585km laying ,424nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |