| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Feb 2024 | 37.9456km laying and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 14 Feb 2024 | 36.3845km laying and laying work in progress. | Perlassery Sn 2 AE | |
| 07 Feb 2024 | 34.6945km laying and laying work in progress. | Perlassery Sn 2 AE | |
| 29 Jan 2024 | work in progress. | Perlassery Sn 2 AE | |
| 23 Jan 2024 | Work in progress | Peralasseri PH Sub-Dn - AEE | |
| 11 Jan 2024 | 27.1385km laying and laying work in progress. | Perlassery Sn 2 AE | |
| 20 Dec 2023 | 16.6885km laying and laying work in progress. | Perlassery Sn 2 AE | |
| 14 Dec 2023 | Work in progress | Peralasseri PH Sub-Dn - AEE | |
| 07 Dec 2023 | 13.4695km laying and laying work in progress. | Perlassery Sn 2 AE | |
| 25 Nov 2023 | 10.4165km laying and laying work in progress. | Perlassery Sn 2 AE |