| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Aug 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 13 Aug 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 05 Aug 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 28 Jul 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 19 Jul 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 15 Jul 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 11 Jul 2025 | 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 07 Jul 2025 | 58.26km laying ,3684nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 30 Jun 2025 | 58.26km laying ,3656nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 23 Jun 2025 | 58.26km laying ,3644nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |