| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Sep 2024 | 53.26km laying ,2366nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 23 Sep 2024 | 47.649km laying ,2292nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 18 Sep 2024 | 47.649km laying ,2249nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 09 Sep 2024 | 47.649km laying ,2082nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 04 Sep 2024 | 44.78km laying ,2023nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 30 Aug 2024 | 44.78km laying ,1911nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 21 Aug 2024 | 44.78km laying ,1757nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 13 Aug 2024 | 44.642km laying ,1575nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 09 Aug 2024 | 44.642km laying ,1518nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 05 Aug 2024 | 44.642km laying ,1441nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |