Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Feb 2024 | 34.6945km laying and laying work in progress. | Perlassery Sn 2 AE | |
29 Jan 2024 | work in progress. | Perlassery Sn 2 AE | |
23 Jan 2024 | Work in progress | Peralasseri PH Sub-Dn - AEE | |
11 Jan 2024 | 27.1385km laying and laying work in progress. | Perlassery Sn 2 AE | |
20 Dec 2023 | 16.6885km laying and laying work in progress. | Perlassery Sn 2 AE | |
14 Dec 2023 | Work in progress | Peralasseri PH Sub-Dn - AEE | |
07 Dec 2023 | 13.4695km laying and laying work in progress. | Perlassery Sn 2 AE | |
25 Nov 2023 | 10.4165km laying and laying work in progress. | Perlassery Sn 2 AE | |
18 Nov 2023 | Pipe supply, 7.395km laying and laying work in progress. | Perlassery Sn 2 AE | |