Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Sep 2024 | 47.649km laying ,2249nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
09 Sep 2024 | 47.649km laying ,2082nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
04 Sep 2024 | 44.78km laying ,2023nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
30 Aug 2024 | 44.78km laying ,1911nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
21 Aug 2024 | 44.78km laying ,1757nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
13 Aug 2024 | 44.642km laying ,1575nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
09 Aug 2024 | 44.642km laying ,1518nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
05 Aug 2024 | 44.642km laying ,1441nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
05 Aug 2024 | 44.642km laying ,1407nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
01 Aug 2024 | 44.642km laying ,1407nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |