| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Feb 2025 | 58.26km laying ,3466nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 27 Jan 2025 | 58.26km laying ,3430nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 22 Jan 2025 | 58.26km laying ,3421nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 17 Jan 2025 | 58.26km laying ,3421nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 13 Jan 2025 | 58.26km laying ,3421nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 09 Jan 2025 | 58.26km laying ,3421nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 04 Jan 2025 | 58.26km laying ,3421nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 31 Dec 2024 | 58.26km laying ,3411nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 21 Dec 2024 | 58.26km laying ,3364nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 17 Dec 2024 | 58.26km laying ,3356nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |