| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Oct 2024 | 56.696km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 19 Oct 2024 | 65.93km laying ,2546nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 19 Oct 2024 | 65.93km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 16 Oct 2024 | 56.696km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 08 Oct 2024 | 56.356km laying ,2455nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 04 Oct 2024 | 55.396km laying ,2413nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 30 Sep 2024 | 53.26km laying ,2366nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 23 Sep 2024 | 47.649km laying ,2292nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 18 Sep 2024 | 47.649km laying ,2249nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 09 Sep 2024 | 47.649km laying ,2082nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |