| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Nov 2024 | 58.26km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 06 Nov 2024 | 57.16km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 02 Nov 2024 | 57.176km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 28 Oct 2024 | 56.888km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 22 Oct 2024 | 56.696km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 19 Oct 2024 | 65.93km laying ,2546nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 19 Oct 2024 | 65.93km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 16 Oct 2024 | 56.696km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 08 Oct 2024 | 56.356km laying ,2455nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
| 04 Oct 2024 | 55.396km laying ,2413nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |