Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 May 2024 | 44.5585km laying ,424nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
10 May 2024 | 42.3445km laying ,424nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
25 Apr 2024 | 42.3445km laying ,340nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
18 Apr 2024 | 42.3445km laying ,319FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
06 Apr 2024 | 42.3445km laying ,266FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
27 Mar 2024 | 41.9365km laying ,266FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
18 Mar 2024 | 40.7165km laying ,950 HTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
11 Mar 2024 | 37.9465km laying ,950 HTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
28 Feb 2024 | 37.9456km laying and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
14 Feb 2024 | 36.3845km laying and laying work in progress. | Perlassery Sn 2 AE |