Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Feb 2026 60km laying ,3803nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
02 Feb 2026 58.26km laying ,3803nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
22 Jan 2026 58.26km laying ,3787nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
14 Jan 2026 58.26km laying ,3776nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
05 Jan 2026 58.26km laying ,3766nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
23 Dec 2025 58.26km laying ,3766nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
15 Dec 2025 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
09 Dec 2025 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
02 Dec 2025 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
25 Nov 2025 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE