Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jun 2025 58.26km laying ,3656nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
23 Jun 2025 58.26km laying ,3644nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
17 Jun 2025 58.26km laying ,3638nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
12 Jun 2025 58.26km laying ,3638nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
05 Jun 2025 58.26km laying ,3613nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
27 May 2025 58.26km laying ,3613nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
21 May 2025 58.26km laying ,3591nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
15 May 2025 58.26km laying ,3591nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
07 May 2025 58.26km laying ,3550nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
03 May 2025 58.26km laying ,3488nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE