Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Dec 2024 58.26km laying ,3364nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
17 Dec 2024 58.26km laying ,3356nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
13 Dec 2024 58.26km laying ,3356nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
09 Dec 2024 58.26km laying ,3343 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
02 Dec 2024 58.26km laying ,3270 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
28 Nov 2024 58.26km laying ,3198 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
23 Nov 2024 58.26km laying ,3030 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
18 Nov 2024 58.26km laying ,2835 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
12 Nov 2024 58.26km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
06 Nov 2024 57.16km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE