| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jun 2025 | 58.26km laying ,3638nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 12 Jun 2025 | 58.26km laying ,3638nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 05 Jun 2025 | 58.26km laying ,3613nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 27 May 2025 | 58.26km laying ,3613nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 21 May 2025 | 58.26km laying ,3591nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 15 May 2025 | 58.26km laying ,3591nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 07 May 2025 | 58.26km laying ,3550nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 03 May 2025 | 58.26km laying ,3488nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 28 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 22 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |