Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2024 | 57.176km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
28 Oct 2024 | 56.888km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
22 Oct 2024 | 56.696km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
19 Oct 2024 | 65.93km laying ,2546nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
19 Oct 2024 | 65.93km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
16 Oct 2024 | 56.696km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
08 Oct 2024 | 56.356km laying ,2455nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
04 Oct 2024 | 55.396km laying ,2413nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
30 Sep 2024 | 53.26km laying ,2366nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE | |
23 Sep 2024 | 47.649km laying ,2292nos.FHTC provided and Pachikkad tank work in progress. | Perlassery Sn 2 AE |