Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2024 57.176km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
28 Oct 2024 56.888km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
22 Oct 2024 56.696km laying ,2794 nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
19 Oct 2024 65.93km laying ,2546nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
19 Oct 2024 65.93km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
16 Oct 2024 56.696km laying ,2521nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
08 Oct 2024 56.356km laying ,2455nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
04 Oct 2024 55.396km laying ,2413nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
30 Sep 2024 53.26km laying ,2366nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE
23 Sep 2024 47.649km laying ,2292nos.FHTC provided and Pachikkad tank work in progress. Perlassery Sn 2 AE