| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Aug 2022 | Work in progress 75% pipe supply completed. 1st & part bill submitted.3000m pipe laid | Koothuparamba Proj AE 2 | |
| 01 Aug 2022 | Work in progress 75% pipe supply completed. 1st & part bill submitted.2400m pipe laid | Koothuparamba Proj AE 2 | |
| 26 Jul 2022 | Work in progress 75% pipe supply completed. 1st & part bill submitted.2000m pipe laid | Koothuparamba Proj AE 2 | |
| 09 Jul 2022 | Pipe line laying work started | Koothuparamba Proj AE 2 | |
| 01 Jul 2022 | Work started | Koothuparamba Proj AE 2 |