| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Oct 2023 | Completed, and commissioned | Koothuparamba Proj AE 2 | |
| 10 Aug 2023 | Work completed | Koothuparamba Proj AE 2 | |
| 31 Jul 2023 | Work completed | Koothuparamba Proj AE 2 | |
| 29 Jul 2023 | 700 FHTCs given | Koothuparamba Proj AE 2 | |
| 26 Jul 2023 | Out of 700no FHTCs ,610nos given | Koothuparamba Proj AE 2 | |
| 19 Jul 2023 | Out of 700no FHTCs ,600nos given | Koothuparamba Proj AE 2 | |
| 14 Jul 2023 | Out of 700no FHTCs ,550nos given | Koothuparamba Proj AE 2 | |
| 11 Jul 2023 | Out of 700no FHTCs ,500nos given | Koothuparamba Proj AE 2 | |
| 05 Jul 2023 | Work in progress 65000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed | Koothuparamba Proj AE 2 | |
| 30 Jun 2023 | Work in progress 64000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed | Koothuparamba Proj AE 2 |