Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Feb 2023 | Work in progress 55890m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
23 Feb 2023 | Work in progress 55850m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
20 Feb 2023 | Work in progress 55800m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
17 Feb 2023 | Work in progress 55700m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
15 Feb 2023 | Work in progress 55500m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
10 Feb 2023 | Work in progress 55300m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
08 Feb 2023 | Work in progress 55000m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
01 Feb 2023 | Work in progress 54700m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
28 Jan 2023 | Work in progress 54600m pipe laid Interconnection and charging work for already laid line in progress | Koothuparamba Proj AE 2 | |
25 Jan 2023 | Work in progress 54300m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 |