Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Apr 2023 Work in progress 56800m pipe laid Interconnection and charging work for already laid line in progress. HTC 200nos completed Koothuparamba Proj AE 2
24 Apr 2023 Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 172nos completed Koothuparamba Proj AE 2
18 Apr 2023 Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 150nos completed Koothuparamba Proj AE 2
10 Apr 2023 Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. HTC 100nos completed Koothuparamba Proj AE 2
05 Apr 2023 Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. HTC 100nos completed Koothuparamba Proj AE 2
30 Mar 2023 Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. second and part bill given Koothuparamba Proj AE 2
18 Mar 2023 Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progres Koothuparamba Proj AE 2
09 Mar 2023 Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progres Koothuparamba Proj AE 2
02 Mar 2023 Work in progress ,Interconnection and charging work for already laid line in progress Koothuparamba Proj AE 2
01 Mar 2023 Work in progress ,Interconnection and charging work for already laid line in progress Koothuparamba Proj AE 2