Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Jun 2023 Work in progress 63100m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
19 Jun 2023 Work in progress 63000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
12 Jun 2023 Work in progress 62500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
06 Jun 2023 Work in progress 62000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
01 Jun 2023 Work in progress 61000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
25 May 2023 Work in progress 60500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
22 May 2023 Work in progress 60000m pipe laid Interconnection and charging work for already laid line in progress. HTC 450nos completed Koothuparamba Proj AE 2
17 May 2023 Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 300nos completed Koothuparamba Proj AE 2
10 May 2023 Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 270nos completed Koothuparamba Proj AE 2
04 May 2023 Work in progress 57200m pipe laid Interconnection and charging work for already laid line in progress. HTC 250nos completed Koothuparamba Proj AE 2