Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Dec 2022 | Work in progress 35400m pipe laid and pressure test for Pipe is in progress | Koothuparamba Proj AE 2 | |
28 Dec 2022 | Work in progress, 35000m pipe laid | Koothuparamba Proj AE 2 | |
17 Dec 2022 | Work in progress 30000 m pipe laid | Koothuparamba Proj AE 2 | |
08 Dec 2022 | Work in progress 27200 m pipe laid | Koothuparamba Proj AE 2 | |
30 Nov 2022 | Work in progress 26200 m pipe laid | Koothuparamba Proj AE 2 | |
23 Nov 2022 | 34 % of work completed 25000 m pipe laid | Koothuparamba Proj AE 2 | |
19 Nov 2022 | Work in progress.24325m pipe laid | Koothuparamba Proj AE 2 | |
14 Nov 2022 | Work in progress.24300m pipe laid. DI pipe laying completed. | Koothuparamba Proj AE 2 | |
02 Nov 2022 | Work in progress 75% pipe supply completed. 1st & part bill submitted.17500m pipe laid | Koothuparamba Proj AE 2 | |
27 Oct 2022 | Work in progress 75% pipe supply completed. 1st & part bill submitted.16600m pipe laid | Koothuparamba Proj AE 2 |