Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Oct 2023 Completed, and commissioned Koothuparamba Proj AE 2
10 Aug 2023 Work completed Koothuparamba Proj AE 2
31 Jul 2023 Work completed Koothuparamba Proj AE 2
29 Jul 2023 700 FHTCs given Koothuparamba Proj AE 2
26 Jul 2023 Out of 700no FHTCs ,610nos given Koothuparamba Proj AE 2
19 Jul 2023 Out of 700no FHTCs ,600nos given Koothuparamba Proj AE 2
14 Jul 2023 Out of 700no FHTCs ,550nos given Koothuparamba Proj AE 2
11 Jul 2023 Out of 700no FHTCs ,500nos given Koothuparamba Proj AE 2
05 Jul 2023 Work in progress 65000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2
30 Jun 2023 Work in progress 64000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed Koothuparamba Proj AE 2