| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jan 2023 | Work in progress 54100m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 19 Jan 2023 | Work in progress 54000m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 18 Jan 2023 | Work in progress 52500m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 16 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 13 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 11 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
| 10 Jan 2023 | Work in progress 52000m pipe laid | Koothuparamba Proj AE 2 | |
| 06 Jan 2023 | Work in progress 48100m pipe laid | Koothuparamba Proj AE 2 | |
| 04 Jan 2023 | Work in progress 48000m pipe laid | Koothuparamba Proj AE 2 | |
| 31 Dec 2022 | Work in progress 35600m pipe laid and pressure test for Pipe is in progress | Koothuparamba Proj AE 2 |