Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jan 2023 | Work in progress 54100m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
19 Jan 2023 | Work in progress 54000m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
18 Jan 2023 | Work in progress 52500m pipe laid Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
16 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
13 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
11 Jan 2023 | Interconnection and charging work for already laid line in progress. | Koothuparamba Proj AE 2 | |
10 Jan 2023 | Work in progress 52000m pipe laid | Koothuparamba Proj AE 2 | |
06 Jan 2023 | Work in progress 48100m pipe laid | Koothuparamba Proj AE 2 | |
04 Jan 2023 | Work in progress 48000m pipe laid | Koothuparamba Proj AE 2 | |
31 Dec 2022 | Work in progress 35600m pipe laid and pressure test for Pipe is in progress | Koothuparamba Proj AE 2 |