Project | JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21 |
---|---|
Project Code | KLMJJM08203262P1 |
Type | Package |
Main Project | JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21 |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 190500000 |
TS Number | TS/2020-21/2020/16227 |
Technical specification | FHTC s for 8802 numbers PVC Pipe, 8kg/cm2, 50mm Dia.- 20000m PVC Pipe, 8kg/cm2, 63mm Dia.-10000m PVC Pipe, 8kg/cm2, 75mm Dia.-10000m PVC Pipe, 8kg/cm2, 90mm Dia.-10000m PVC Pipe, 8kg/cm2, 110mm Dia.-15000m PVC Pipe, 8kg/cm2, 160mm Dia.-5000m 150mm GI medium class Pipes- 200m 100mm GI medium class Pipes-200m |
Contractor | M/s. Tomco Engineering (P) Ltd (Mob: 9447082222) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Jul 2021 | Pending | 11 Aug 2021 | Road Cut Related Risk | Demand received from PWD proposed HDD method for two DLP roads | No comments added. | Action Taken |
31 May 2021 | Pending | 15 Aug 2021 | Risks From Other Projects | Unidentified JICA gaps | No comments added. | Action Taken |
20 Feb 2021 | Pending | 10 Apr 2021 | Contract Related Risks | Delay in supply in pipes and materials at site | No comments added. | Action Taken |
01 Feb 2021 | Pending | 31 Aug 2021 | Road Cut Related Risk | Jica line gaps and line to be laid for about 23 km in PWD Roads | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 31 Jul 2023 |
Expected date of Completion | 30/07/2023 |
TS Date | 12 Sep 2020 |
---|---|
Estimate Approval | 12 Sep 2020 |
NIT Approval | 16 Nov 2020 |
Tender Closing | 25 Nov 2020 |
Technichal Pre-Qualification | 27 Nov 2020 |
Price bid opening | 29 Nov 2020 |
Workorder Date | 28 Dec 2020 |
---|---|
NA | 10 Feb 2021 |
Kollam Project HD |
Date: 26/06/2024 |
Work has been completed | 100% Completed
work completed and line commissioned.. 25 numbers HTCs due to elevated zone .
Kollam Project HD |
Date: 24/06/2024 |
Work in progress | 86% Completed
Leak rectification progress....