JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21

Project JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Project Code KLMJJM08203262P1
Type Package
Main Project JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 190500000
TS Number TS/2020-21/2020/16227
Technical specification FHTC s for 8802 numbers PVC Pipe, 8kg/cm2, 50mm Dia.- 20000m PVC Pipe, 8kg/cm2, 63mm Dia.-10000m PVC Pipe, 8kg/cm2, 75mm Dia.-10000m PVC Pipe, 8kg/cm2, 90mm Dia.-10000m PVC Pipe, 8kg/cm2, 110mm Dia.-15000m PVC Pipe, 8kg/cm2, 160mm Dia.-5000m 150mm GI medium class Pipes- 200m 100mm GI medium class Pipes-200m
Contractor M/s. Tomco Engineering (P) Ltd (Mob: 9447082222)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
10 Jul 2021 Pending 11 Aug 2021 Road Cut Related Risk Demand received from PWD proposed HDD method for two DLP roads No comments added. Action Taken
31 May 2021 Pending 15 Aug 2021 Risks From Other Projects Unidentified JICA gaps No comments added. Action Taken
20 Feb 2021 Pending 10 Apr 2021 Contract Related Risks Delay in supply in pipes and materials at site No comments added. Action Taken
01 Feb 2021 Pending 31 Aug 2021 Road Cut Related Risk Jica line gaps and line to be laid for about 23 km in PWD Roads No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/02/2021
Scheduled date of Completion as per agreement 31 Jul 2023
Expected date of Completion 30/07/2023

Processing Dates

TS Date 12 Sep 2020
Estimate Approval 12 Sep 2020
NIT Approval 16 Nov 2020
Tender Closing 25 Nov 2020
Technichal Pre-Qualification 27 Nov 2020
Price bid opening 29 Nov 2020

Approval Dates

Workorder Date 28 Dec 2020
NA 10 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 26/06/2024

Work has been completed | 100% Completed

work completed and line commissioned.. 25 numbers HTCs due to elevated zone .

Kollam Project HD
Date: 24/06/2024

Work in progress | 86% Completed

Leak rectification progress....