Phase II works- pipe line extension work and providing 2440 FHTCs -Pipeline Work

Project Phase II works- pipe line extension work and providing 2440 FHTCs -Pipeline Work
Project Code KLMJJM08203262P5
Type Package
Main Project JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Phase II works- pipe line extension work and providing 2440 FHTCs -Pipeline Work
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 116700000
TS Number WRD/KWA-CE(SR)/EST_TS/6986/2022_26_6_5 Dated: 20-11-2023
Technical specification 2440 FHTC Distribution and line extension

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/10/2023
Scheduled date of Completion as per agreement 07 Jun 2025
Expected date of Completion 07/06/2025

Processing Dates

TS Date 20 Nov 2023
Estimate Approval 20 Nov 2023
NIT Approval 30 Nov 2023
Tender Closing 13 Dec 2023
Technichal Pre-Qualification 16 Dec 2023
Price bid opening 22 Dec 2023

Approval Dates

Workorder Date 28 Feb 2024
NA 07 Jun 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 29/06/2024

Work in progress | 1% Completed

Agreement executed on 7.06.2024 and request submitted to CIPET for pipe testing on 20.06.2024.

Kollam Project HD
Date: 28/06/2024

Work in progress | 1% Completed

Agreement executed on 7.06.2024 and request submitted to CIPET for pipe testing on 20.06.2024.