JJM- Veliyam Grama Panchayath - Phase I -Part II-Balance work for pipe line extension and JICA gap closing works

Project JJM- Veliyam Grama Panchayath - Phase I -Part II-Balance work for pipe line extension and JICA gap closing works
Project Code KLMJJM08203262P2
Type Package
Main Project JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM- Veliyam Grama Panchayath - Phase I - Part II- Balance work for pipe line extension and JICA gap closing works
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 23730000
TS Number TS/2022-2023/2022/12847 dated 16-07-2022
Technical specification Pipe line extension and jica line gap works
Contractor SATHEESH KUMAR T (Mob: 9809825259)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/08/2022
Scheduled date of Completion as per agreement 30 Jun 2023
Expected date of Completion 30/06/2023

Processing Dates

TS Date 16 Jul 2022
Estimate Approval 15 Jul 2022
NIT Approval 31 Jul 2022
Tender Closing 17 Aug 2022
Technichal Pre-Qualification 22 Aug 2022
Price bid opening 24 Aug 2022

Approval Dates

Workorder Date 03 Sep 2022
NA 28 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 27/06/2023

Work has been completed | 100% Completed

Work completed and final bill submitted.

Kollam Project HD
Date: 26/06/2023

Work has been completed | 100% Completed

Work completed and final bill submitted on 09-06-2023..