Project | JJM- Veliyam Grama Panchayath - Phase I -Part II-Balance work for pipe line extension and JICA gap closing works |
---|---|
Project Code | KLMJJM08203262P2 |
Type | Package |
Main Project | JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- Veliyam Grama Panchayath - Phase I - Part II- Balance work for pipe line extension and JICA gap closing works |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 23730000 |
TS Number | TS/2022-2023/2022/12847 dated 16-07-2022 |
Technical specification | Pipe line extension and jica line gap works |
Contractor | SATHEESH KUMAR T (Mob: 9809825259) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/08/2022 |
---|---|
Scheduled date of Completion as per agreement | 30 Jun 2023 |
Expected date of Completion | 30/06/2023 |
TS Date | 16 Jul 2022 |
---|---|
Estimate Approval | 15 Jul 2022 |
NIT Approval | 31 Jul 2022 |
Tender Closing | 17 Aug 2022 |
Technichal Pre-Qualification | 22 Aug 2022 |
Price bid opening | 24 Aug 2022 |
Workorder Date | 03 Sep 2022 |
---|---|
NA | 28 Dec 2022 |
Kollam Project HD |
Date: 27/06/2023 |
Work has been completed | 100% Completed
Work completed and final bill submitted.
Kollam Project HD |
Date: 26/06/2023 |
Work has been completed | 100% Completed
Work completed and final bill submitted on 09-06-2023..