Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
08 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
06 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
05 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
04 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
03 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
02 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
01 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
31 Mar 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
30 Mar 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 |