Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
22 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
20 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
19 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
18 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
17 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
16 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
15 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
12 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
11 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 |