Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 May 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
04 May 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
03 May 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
02 May 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
30 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
29 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
27 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
26 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
25 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
24 Apr 2024 | WORK IN PROGRESS. 1036 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 |