Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 May 2024 | Work in progress. 1107 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
30 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
29 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
27 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
25 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
24 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
23 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
21 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
20 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
18 May 2024 | Work in progress. 1083 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 |