| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Nov 2020 | RWPM- 19.95 km pipe laying completed | Nattika Project Dn AE 6 | |
| 17 Nov 2020 | WTP -Kottapadi – 85% completed.Balance work is in progress. Well cum Pump house -- All works completed (90%).Transformer supplied and is to be erected. RWPM-84% pipe supplied ( 33.23Km). 50.20% Laying work completed (19.824 Km). Jointing of 42 joints HDPE pipe completed. | Nattika Project Dn AE 5 | |
| 13 Nov 2020 | RWPM-33.233 km pipe supplied .Jointing of 42 joints HDPE pipe completed. | Nattika Project Dn AE 6 | |
| 13 Nov 2020 | 33.233 km pipe supplied. Jointing of 42 joints HDPE pipe completed. | Nattika Project Dn AE 6 | |
| 13 Nov 2020 | RWPM - 19.56km pipe laying completed. 67% of work completed | Nattika Project Dn AE 5 | |
| 11 Nov 2020 | Intake well cum pump house - 90% completed. Only transformer erection work and electrical works pending 15MLD WTP Kottapadi - 80% completed. Finishing works and electrical works balance | Nattika Project Dn AE 5 | |
| 08 Sep 2020 | Intake well cum pump house - 80% completed. 15MLD WTP Kottapadi - 70% completed - Civil structure works completed. | Nattika Project Dn AE 5 | |
| 11 Aug 2020 | Intake well cum pump house - 80% completed. 15MLD WTP Kottapadi - 65% completed Over all 72.5% work completed | Nattika Project Dn AE 5 | |
| 07 Jul 2020 | Intake well cum pump house - 80% completed. 15MLD WTP Kottapadi - 60% completed | Nattika Project Dn AE 5 | |
| 07 Jul 2020 | Over all 70% work completed. | Nattika Project Dn AE 5 |