Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Feb 2021 | Gap closing work of package 4 along municipal roads at Kattachira area is in progress | Kottayam AE 3 | |
24 Feb 2021 | Meeting with MLA on 23/2/21 and promised involve to solve present crisis | Kottayam AE 3 | |
22 Feb 2021 | Meeting with MLA on 22/2/21 postponed to 23/2/21 for the Convenience of MLA | Kottayam AE 3 | |
20 Feb 2021 | expert committee meeting conducted work stopped due to PWD road sanction issue once again contacted MLA for a joint meeting | Kottayam AE 3 | |
17 Feb 2021 | first expert committee meeting will be held on 17/2/21 | Kottayam AE 3 | |
15 Feb 2021 | higher level interventions needed and inter departmental issues needs to be settled | Kottayam AE 3 | |
12 Feb 2021 | Expert committee meeting will be conducted on 19.02.2021 | Kottayam AE 3 | |
11 Feb 2021 | Contact concerned section of District Collector .They informed the date not allot by the District Collector | Kottayam AE 3 | |
10 Feb 2021 | Land acquisition- expert committee meeting file with DC for convene the meeting. | Kottayam AE 3 | |
02 Feb 2021 | Approach District collector for high level ntervention | Kottayam AE 3 |