KIIFB 2017-18- Drinking water project in Ettumanoor Municipality

Project KIIFB 2017-18- Drinking water project in Ettumanoor Municipality
Project Code KTMKIIFB0619525
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description A new scheme sanctioned under KIIFB 2017-18 for supplying water to the entire area of Ettumanoor Municipality . Benefitting a population of 79202. Capacity of WTP is 22mld
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 932250000
AS Number G.O Rt. No:227/2018/WRD
TS Amount (Rs) 117400000
TS Number TS/2019-2020/2019/19040 Dated: 31-01-2020
Total Bill Submitted (Rs) 53418291
Total Bill Paid (Rs) 53418291
Population Benefitted 79202
Capacity in MLD 22.00
Actual Project Completion Date 31 Dec 2023
Coverage Ettumanoor Municipality-100%
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB 2017-18- Drinking water project in Ettumanoor Municipality Package -1 Kottayam Project Dn
2 KIIFB 2017-18- Drinking water project in Ettumanoor Municipality-Package 2 Kottayam Project Dn
3 KIIFB 2017-18- Drinking water project in Ettumanoor Municipality-Package 3 Kottayam Project Dn
4 KIIFB 2017-18- Drinking water project in Ettumanoor Municipality Package IV Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 Package 1,2&3 -Due to non participation for individual tenders phase 1,2,3 is merged and send for techmical sanction to CEs office package 4 -All pipe laying works are completed now. Only road restoration works are pending Kottayam Proj Dn AE4
23 Jan 2023 Package 1:Value of land for construction of 22 MLD WTP at Nethaji Nagar is computed for Rs. 3.34 crores . The amount was deposited by the KIIFB 17.1.2023.This amount has to be given to the LA Thahasildar, KIIFB & this amount has to be given to the owner of the land.-. Package 2:- Estimate send for TS and now in Chief Engineer office. ; Package 3:Estimate preparation works in progress and be completed after the estimates for the Packages 1 &2.-. Package 4:-Road restoration works on Koodalloor road partially completed. The road restoration works in the Manarcad bypass road in progress. The gap connection & the interconnection works in progress . Kottayam Proj Dn AE4
14 Sep 2022 Package 1:-Sub Division sketch is approved. Valuation report is not yet submitted by Tahsildar. Request for revision of Revenue B is made to Additional Chief Secretary, Revenue. The land acquisition is in progress (43.23 Are private land) and the 11(1) notification has been published on 04-07-2021. Subdivision records approved. BVR has been prepared. Resurvey number 29/1 has been incorrectly mentioned in the Revenue (B) department order. The Land Acquisition Officer has issued a letter to the Requisition Authority (KWA) requesting an erratum order (the correct Resurvey number is 21/9), and the District Collector has proposed to the Government for revising the Revenue (B) department's order. KWA Head office has to forward a letter to the Water Resources Department for availing fresh Revenue B Erratum Order. Package 2:- Permissive sanction for handover of 13.5 cent of land at Kacherikunnu was received . The soil investigation completed. The design & estimate preparation works in progress. ; Package 3:- Estimate preparation works in progress and be completed after the estimates for the Packages 1 &2. Package 4:- Initial level taking works in progress in order to start the road restoration works. Meenachal-Malankara Project Dn AEE1
01 Aug 2022 PACKAGE 1 Since there was change in survey number for 107 cent land,revised 11(1) notification is published on 01.07.2022.Sub-Division sketch is approved by surveyor.Valuation report is not submitted bt Tahsildar for next way forward. 19(1) notification and value assessment is being prepared at LA Tahsildr office. PACKAGE 2 Permissive sanction for handover of 13.5 cent land at Kacherikunnu is recieved under JJM Athirampuzha on 24.07.2022 Kottayam Proj Dn AE4
01 Aug 2022 PACKAGE 1 Since there was change in survey number for 107 cent land,revised 11(1) notification is published on 01.07.2022.Sub-Division sketch is approved by surveyor.Valuation report is not submitted bt Tahsildar for next way forward. 19(1) notification and value assessment is being prepared at LA Tahsildr office. for the 1.5 ent revenue land handover,file is pending at office of Land revenu commissionarate,TVM. Kottayam Proj Dn AE4

Project Review

See All Review messages
Review Date Review Message Review Attended By
29 Jun 2021 LAND ACQUISITION DETAILS TO BE ENTERED AEE
04 Feb 2021 Add photographs showing progress of the work AE

Duration & Sanction dates

Date of start of Project 21/05/2020
Scheduled date of Completion of the Project 30 Apr 2022
Expected date of Completion 31/10/2023

Processing Dates

AS Date 31 Mar 2018
TS Date 31 Jan 2020