Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Mar 2021 | PWD sanction pending | Kottayam AE 3 | |
27 Mar 2021 | Package 1-Social Impact Assessment committee conducted on 26.03.2021 ,2.00pm at Muncipal conference Hall in connection with Land Acquistion for constructing 22 MLD WTP and visited the site. | Kottayam AE 3 | |
25 Mar 2021 | Work held up in PWD roads(due to suspension of Engineer in Charge for road cutting),Intervention needed from higher level.Work along Muncipal roads-temporarily stopped. | Kottayam AE 3 | |
24 Mar 2021 | Work held up in PWD roads(due to suspension of Engineer in Charge for road cutting),Intervention needed from higher level.Work along Muncipal roads-temporarily stopped. | Kottayam AE 3 | |
21 Mar 2021 | Work held up in PWD roads(due to suspension of Engineer in Charge for road cutting),Intervention needed from higher level.Work along Muncipal roads-temporarily stopped. | Kottayam AE 3 | |
17 Mar 2021 | Current status of packages are as follows: PACKAGE 1:- EIA(Environmental Impact Assessment) committee for Land Acquistion for constructing 22 MLD WTP is formed. Acquistion is proposed for land in survey no( 21/1 & 21/1-1).Owner details is as follows :Sri.Varghese Mathew Kuzhiyampackal House Amalagiri P O Kottayam 686561 PACKAGE 2:- Permissive sanction for LA for construction of OHSR at Kacherikunnu is pending at RDO office. Estimate for the package is send for review and approval PACKAGE 3 Estimate for the package is send for review and approval PACKAGE 4 Work held up in PWD roads(due to suspension of Engineer in Charge for road cutting),Intervention needed from higher level. | Kottayam AE 3 | |
16 Mar 2021 | Gap closing work of package 4 along municipal roads at Kattachira area is in progress | Kottayam AE 3 | |
15 Mar 2021 | package recasting needed to suit the AS amount | Kottayam AE 3 | |
14 Mar 2021 | Gap closing work of package 4 along municipal roads at Kattachira area is in progress | Kottayam AE 3 | |
12 Mar 2021 | Gap closing work of package 4 along municipal roads at Kattachira area is in progress | Kottayam AE 3 |