Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jun 2021 General Status: Due to the rate revision in PRICE software (updated SoR), sum of package wise estimate exceeded AS amount. Hence redirected from HO for revision. Package I Social Impact Assessment committee conducted on 26.03.2021 and report submitted to Dist.Collector on 26.05.21. On 02.06.2021, letter obtained from Dist. Collector seeking the opinion of KWA in SIA (Social Impact Assessment) report. Hon.minister Sri. V N Vasavan ensured to conduct a joint meeting with revenue officials & KWA officials to speed up land Acquisition process (purchasing of 107 cents at Nethaji Nagar and 13.5 cents at Kacherikunnu for permissive sanction and the meeting is proposed to be conducted on Saturday (05.06.2021) at Kottayam collectorate. Package II Permissive sanction for LA (Land Acquistion) to construct OHSR at Kacherikunnu is pending at RDO office. On 02.06.2021, meeting was conducted with Tahsildar, Kottayam and requested for speeding up the process. Hon.minister Sri. V N Vasavan ensured to conduct a joint meeting with revenue officials & KWA officials to speed up land Acquisition process (purchasing of 107 cents at Nethaji Nagar and 13.5 cents at Kacherikunnu for permissive sanction and the meeting is proposed to be conducted on Saturday (05.06.2021) at Kottayam collectorate. Package III Due to the rate revision in PRICE software (updated SoR), sum of package wise estimate exceeded AS amount. Hence estimate is redirected from HO for revision. Package IV Permission to lay pipes on PWD roads obtained from PWD officials. However due to monsoon ban, work is held up. Kottayam AE 3
26 May 2021 The total estimate amount of whole 4 packages exceeded from original AS amount of 93.225 crore due to revision of rates. The estimate has to be revised Kottayam AE 3
19 May 2021 Communicated the decision of meeting conducted by Sri V N Vasavan MLA to the contractor and directed to restart the work without delay Kottayam AE 3
18 May 2021 Meeting chaired by the newly Elected MLA of Ettumanoor with PWD Officials conducted on 17.05.2021 and decision taken to restart the pipe laying work in PWD roads. Kottayam AE 3
15 May 2021 Meeting conducted with newly Elected MLA of Ettumanoor and discussed the PWD issue in detail. Kottayam AE 3
13 May 2021 Work-nil Kottayam AE 3
11 May 2021 Met newly Elected MLA of Ettumanoor and discussed the issue in detail. He promised to conduct meeting soon to resolve the issue. Draft copy of assessment on environmental impact assessment study was received from The Chairman and will be available soon Kottayam AE 3
27 Apr 2021 Work-nil Kottayam AE 3
23 Apr 2021 Work-nil Kottayam AE 3
22 Apr 2021 Work-nil Kottayam AE 3