Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Jun 2021 | ongoing | Neyyattinkara WS Dn EE | |
18 Jun 2021 | Beneficiary list collected | Neyyattinkara WS Dn EE | |
01 Jun 2021 | As panchayath area is in critical containment zone the work is not in progress. | Neyyattinkara WS Dn EE | |
27 May 2021 | due to lockdown the work is not in progress | Neyyattinkara WS Dn EE | |
20 May 2021 | As the panchayath area is Containment zone and the Lock down declared by the State Govt. the work is not in progress. | Neyyattinkara WS Dn EE | |
29 Mar 2021 | ON GOING | Neyyattinkara WS Dn EE | |
11 Feb 2021 | Agreement not executed by the contractor, Sri.R.Suraj | Neyyattinkara WS Dn EE | |
30 Nov 2020 | Ongoing | Neyyattinkara WS Dn EE |