Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Nov 2021 | Work has been interrupted due to heavy rain on 25/11/2021 and 26/11/2021. | Neyyattinkara WS Dn EE | |
25 Nov 2021 | Out of 3000 connections , 1537 connections are given . | Neyyattinkara WS Dn EE | |
20 Nov 2021 | Out of 3000 connections , 1475 connections are given . | Neyyattinkara WS Dn EE | |
20 Nov 2021 | Out of 3000 connections , 1450 connections are given. | Neyyattinkara WS Dn EE | |
19 Nov 2021 | Out of 3000 connections, 1400 connections are given | Neyyattinkara WS Dn EE | |
15 Nov 2021 | Work delay due to the heavy rain fall and flood | Neyyattinkara WS Dn EE | |
12 Nov 2021 | Out of 3000 connections , 1354 connections are given. | Neyyattinkara WS Dn EE | |
07 Nov 2021 | Out of 3000 connections ,1275 connections are given | Neyyattinkara WS Dn EE | |
05 Nov 2021 | Out of 3000 connections, 1254 connections are given | Neyyattinkara WS Dn EE | |