Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Sep 2021 | Out of 3000 connections,743 connections are given. | Neyyattinkara WS Dn EE | |
25 Sep 2021 | Out of 3000 connections ,717 connections are given. | Neyyattinkara WS Dn EE | |
23 Sep 2021 | Out of 3000 connections 690 connections are given. | Neyyattinkara WS Dn EE | |
13 Sep 2021 | Out of 3000 connections, 625 connections are done. | Neyyattinkara WS Dn EE | |
10 Sep 2021 | Out of 3000 connections, 588 connections are given | Neyyattinkara WS Dn EE | |
07 Sep 2021 | CC 2nd part bill for 247 connections are given, out of 3000 connections 538 connections are given. | Neyyattinkara WS Dn EE | |
04 Sep 2021 | Out of 3000 connections, 505 FHTCS are given | Neyyattinkara WS Dn EE | |
01 Sep 2021 | Out of 3000 connections, 459 FHTCS are given. | Neyyattinkara WS Dn EE | |
30 Aug 2021 | Out of 3000 connections, 400 connections are given. | Neyyattinkara WS Dn EE | |