Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2021 | Out of 3000 connections, 1191 connections are given | Neyyattinkara WS Dn EE | |
30 Oct 2021 | Out of 3000 connections, 1179 connections are given | Neyyattinkara WS Dn EE | |
27 Oct 2021 | Out of 3000 connections, 1125 connections are given | Neyyattinkara WS Dn EE | |
26 Oct 2021 | Out of 3000 connections , 1102 connections are given. | Neyyattinkara WS Dn EE | |
16 Oct 2021 | In Venganoor panchayath Ward nos. 6,8,11,12,19 and 20 are in critical containment zone.It will affect the progress of work. | Neyyattinkara WS Dn EE | |
16 Oct 2021 | Out of 3000 connections 960 FHTCS are done | Neyyattinkara WS Dn EE | |
12 Oct 2021 | Out of 3000 connections 912 FHTCS are given, also out of 8300 m pipe line extension 4900 m is done | Neyyattinkara WS Dn EE | |
09 Oct 2021 | Out of 3000 connections, 902 connections are given. | Neyyattinkara WS Dn EE | |
06 Oct 2021 | part bill for 800 connections are given | Neyyattinkara WS Dn EE | |
02 Oct 2021 | Out of 3000 connections , 803 connections are given | Neyyattinkara WS Dn EE |