Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Aug 2021 | Out of 3000 connections, 340 connections are given. | Neyyattinkara WS Dn EE | |
22 Aug 2021 | Out of 3000 connections, 300 connections are given. | Neyyattinkara WS Dn EE | |
13 Aug 2021 | Work is going on | Neyyattinkara WS Dn EE | |
05 Aug 2021 | 258 FHTCS are given out of 3000 connections. Also cc1st and part bill for 258 connections are given. | Neyyattinkara WS Dn EE | |
23 Jul 2021 | 167 FHTCS are given out of 3000 connections. | Neyyattinkara WS Dn EE | |
19 Jul 2021 | 140 FHTCS are given out of 3000 connections. | Neyyattinkara WS Dn EE | |
15 Jul 2021 | 95 FHTCS are given out of 3000 connections. | Neyyattinkara WS Dn EE | |
14 Jul 2021 | 83FHTCS are given out of 3000 connections. | Neyyattinkara WS Dn EE | |
06 Jul 2021 | 38FHTCS are given out of 3000 FHTCS | Neyyattinkara WS Dn EE | |
30 Jun 2021 | ongoing | Neyyattinkara WS Dn EE |