Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jan 2022 | wide spreading of Covid 19 affected the progress of work. | Neyyattinkara WS Dn EE | |
21 Jan 2022 | EWE for pipe laying in Vavvamoola lake road | Neyyattinkara WS Dn EE | |
20 Jan 2022 | 2090 FHTCS are given out of 3000 FHTCS. Also wide spreading of COVID19 in all wards of Venganoor pht. affected the progress of work | Neyyattinkara WS Dn EE | |
10 Jan 2022 | 2070 FHTCS are given out of 3000 FHTCS. | Neyyattinkara WS Dn EE | |
06 Jan 2022 | 2025 FHTCS are given out of 3000 FHTCS. Also CC Eighth and part bill for 2001 FHTCS are submitted. | Neyyattinkara WS Dn EE | |
02 Jan 2022 | Out of 3000 FHTCS, 2000 FHTCS are given. | Neyyattinkara WS Dn EE | |
29 Dec 2021 | Out of 3000 connections, 1860 connections are given | Neyyattinkara WS Dn EE | |
23 Dec 2021 | Out of 3000 connections , 1850 connections are given | Neyyattinkara WS Dn EE | |
21 Dec 2021 | Out of 3000 connections, 1826 connections are given . | Neyyattinkara WS Dn EE | |
20 Dec 2021 | Out of 3000 connections , 1816 connections are given . | Neyyattinkara WS Dn EE |