Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jan 2022 wide spreading of Covid 19 affected the progress of work. Neyyattinkara WS Dn EE
21 Jan 2022 EWE for pipe laying in Vavvamoola lake road Neyyattinkara WS Dn EE
20 Jan 2022 2090 FHTCS are given out of 3000 FHTCS. Also wide spreading of COVID19 in all wards of Venganoor pht. affected the progress of work Neyyattinkara WS Dn EE
10 Jan 2022 2070 FHTCS are given out of 3000 FHTCS. Neyyattinkara WS Dn EE
06 Jan 2022 2025 FHTCS are given out of 3000 FHTCS. Also CC Eighth and part bill for 2001 FHTCS are submitted. Neyyattinkara WS Dn EE
02 Jan 2022 Out of 3000 FHTCS, 2000 FHTCS are given. Neyyattinkara WS Dn EE
29 Dec 2021 Out of 3000 connections, 1860 connections are given Neyyattinkara WS Dn EE
23 Dec 2021 Out of 3000 connections , 1850 connections are given Neyyattinkara WS Dn EE
21 Dec 2021 Out of 3000 connections, 1826 connections are given . Neyyattinkara WS Dn EE
20 Dec 2021 Out of 3000 connections , 1816 connections are given . Neyyattinkara WS Dn EE