Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 May 2024 | 15000m laying completed, 2070 connections completed, 16 th and part bill submitted | Chavara AE | |
07 May 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted | Chavara AEE | |
04 May 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted | Chavara AE | |
01 May 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted | Chavara AEE | |
28 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted | Chavara AEE | |
25 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted. | Chavara AE | |
22 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted. | Chavara AE | |
19 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted. | Chavara AE | |
16 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted. Leak rectification ongoing | Chavara AE | |
16 Apr 2024 | 15000m laying completed, 2060 connections completed, 16 th and part bill submitted. | Chavara AE |