Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied . Ward no:7,THALACHIRA- AYODYA NAGAR laying work in progress Zone 4B -Pipe layine at Ward 4KANNAMKODU ROAD, Zone 2B Ward9 pipe laying |
Kollam Project Dn AE |
|
16 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied . Ward no:16, Kaduvapara LP school jn -Thalachira temple road,starting post number-CMD/CK/69/18,Node : 682-675-684,PVC (90mm 8kg)pipe laying work in progress Zone 4B -Pipe layine at Ward 19 Panaveli, Zone 2B Ward 11 pipe laying 6kg 90mm kottavattom north |
Kollam Project Dn EE |
|
14 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied .Ward no:16, Kaduvapara Anganavadi road,starting post number-CMD/CK.92/13/A,Node : 583 to 584,PVC (90mm 8kg)pipe laying work in progress , Zone 4B -pipe road,starting post number-CMD/CK.92/13/A,Node : 583 to 584,PVC (90mm 8kg)pipe laying progressin,Zone 2B Pipe Laying progressing at Ward 12 Kottavattom... |
Kollam Project HD |
|
12 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied Work started at Chirattakonam-Pachoor laying progressing, Zone 4B -pipe laying in Ward 19 panaveli , Zone 2B Pipe Laying started Ward 12 Kottavattom... |
Kollam Project Dn AE |
|
10 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied Work started at ward 16Ampalathumvila- Thalachira laying progressing, Zone 4B -pipe laying in panaveli Mahadeva temple, Zone 2B Pipe sLaying started Ward 12 and house connection progressing at ward 5. |
Kollam Project Dn AE |
|
09 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied Work started at ward 16Ampalathumvila- Thalachira laying progressing, Zone 4B -pipe laying in panaveli, Zone 2B Pipe sLaying started Ward 5. |
Kollam Project Dn AE |
|
04 Nov 2022 |
Zone 4A 65.15 PVC pipeline supplied Work started at ward 17 Eettivila, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. |
Kollam Project Dn AE |
|
31 Oct 2022 |
Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. |
Kollam Project Dn AE |
|
29 Oct 2022 |
Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. |
Kollam Project Dn AE |
|
27 Oct 2022 |
Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. |
Kollam Project Dn AE |
|