Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . Ward no:7,THALACHIRA- AYODYA NAGAR laying work in progress Zone 4B -Pipe layine at Ward 4KANNAMKODU ROAD, Zone 2B Ward9 pipe laying Kollam Project Dn AE
16 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . Ward no:16, Kaduvapara LP school jn -Thalachira temple road,starting post number-CMD/CK/69/18,Node : 682-675-684,PVC (90mm 8kg)pipe laying work in progress Zone 4B -Pipe layine at Ward 19 Panaveli, Zone 2B Ward 11 pipe laying 6kg 90mm kottavattom north Kollam Project Dn EE
14 Nov 2022 Zone 4A 65.15 PVC pipeline supplied .Ward no:16, Kaduvapara Anganavadi road,starting post number-CMD/CK.92/13/A,Node : 583 to 584,PVC (90mm 8kg)pipe laying work in progress , Zone 4B -pipe road,starting post number-CMD/CK.92/13/A,Node : 583 to 584,PVC (90mm 8kg)pipe laying progressin,Zone 2B Pipe Laying progressing at Ward 12 Kottavattom... Kollam Project HD
12 Nov 2022 Zone 4A 65.15 PVC pipeline supplied Work started at Chirattakonam-Pachoor laying progressing, Zone 4B -pipe laying in Ward 19 panaveli , Zone 2B Pipe Laying started Ward 12 Kottavattom... Kollam Project Dn AE
10 Nov 2022 Zone 4A 65.15 PVC pipeline supplied Work started at ward 16Ampalathumvila- Thalachira laying progressing, Zone 4B -pipe laying in panaveli Mahadeva temple, Zone 2B Pipe sLaying started Ward 12 and house connection progressing at ward 5. Kollam Project Dn AE
09 Nov 2022 Zone 4A 65.15 PVC pipeline supplied Work started at ward 16Ampalathumvila- Thalachira laying progressing, Zone 4B -pipe laying in panaveli, Zone 2B Pipe sLaying started Ward 5. Kollam Project Dn AE
04 Nov 2022 Zone 4A 65.15 PVC pipeline supplied Work started at ward 17 Eettivila, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. Kollam Project Dn AE
31 Oct 2022 Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. Kollam Project Dn AE
29 Oct 2022 Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. Kollam Project Dn AE
27 Oct 2022 Zone 4A Data collection progressing, Zone 4B -24Km pipe supplied and survey started, Zone 2B Pipe supply started. Kollam Project Dn AE